Implementation Planning
Agree on scope, responsibilities, dependencies, and measurable acceptance criteria.
Progress configuration, integration, and testing in parallel as prerequisites become available.
Use verified results and operational readiness to determine when to launch and expand.
Choose Your Planning Approach
Define the customer and advertiser workflows required for the initial release.
Plan for production data, supported devices, campaign controls, measurement, reporting, monitoring, recovery, and operational ownership.
Acceptance should cover the complete launch scope and the versions being released.
Define the questions the POC must answer, the workflows being evaluated, and the evidence required to demonstrate success.
Identify which components are live, simulated, or excluded. Set an evaluation window and document the work that would remain before production.
POC acceptance and production launch approval are separate milestones.
Illustrative Implementation Schedule
An illustrative 45-day planThe schedule below is a planning example. Confirm whether your project uses calendar days or business days. Actual timing depends on scope, team availability, access, external dependencies, release windows, and approval requirements.
The windows overlap intentionally. Begin component testing during development and start complete journeys as soon as their dependencies are ready.
| Phase | Example window | Primary owners | Exit milestone |
|---|---|---|---|
| Discovery and scope | Days 1–7 | Joint business and technical leads | Scope, owners, success criteria, and dependencies agreed. |
| Data and platform setup | Days 3–14 | Publisher data team and Koddi | Representative data validated; required environment, configuration, and access ready. |
| Integration and component testing | Days 8–30 | Publisher engineering, supported by Koddi | In-scope components work and the complete test journey is available. |
| End-to-end testing and UAT | Days 21–40 | Joint technical, QA, data, and business teams | Acceptance evidence reviewed; launch-blocking defects resolved and retested. |
| Launch preparation | Days 35–44 | Joint launch and operations owners | Readiness decision and rollout plan recorded. |
| Controlled launch | Day 45, subject to readiness | Named launch owners | Production smoke tests pass and initial exposure is verified. |
| Stabilization and handoff | Agreed post-launch window | Joint operations and program teams | Production behavior and operational ownership accepted. |
Phase 1: Discovery and Scope
Illustrative window: Days 1–7
Agree on the initial release and the conditions that will establish success.
Use the Sample Implementation Scope to organize discovery and document the plan.
Decisions and deliverables
| Area | Confirm |
|---|---|
| Program scope | Properties, placements, formats, markets, devices, and customer journeys. |
| Advertiser experience | Access, campaign creation, approvals, funding, creative requirements, and reporting. |
| Integration | Architecture, candidate selection, environments, and deployment dependencies. |
| Data and identity | Entity grain, identifiers, feed attributes, targeting inputs, and identity continuity. |
| Measurement | Conversion definitions, attribution requirements, reporting, and reconciliation. |
| Operations | Monitoring, support, escalation, launch coverage, and recovery. |
| Acceptance | Required tests, thresholds, evidence, and decision-makers. |
| Boundaries | Exclusions, assumptions, dependencies, and deferred capabilities. |
Create a shared delivery plan, decision log, issue tracker, and test tracker.
Schedule working sessions using the Implementation Meetings guide.
Exit milestone: Both teams agree on the launch scope, responsibilities, success criteria, and dependencies that determine the schedule.
Phase 2: Data and Platform Setup
Illustrative window: Days 3–14
Provide representative data early so identifier mapping, ingestion, and configuration can be validated while integration development progresses.
Workstreams and ownership
| Workstream | Publisher responsibility | Koddi responsibility |
|---|---|---|
| Inventory | Supply representative records, stable identifiers, and required attributes. | Configure agreed ingestion and mappings; support validation. |
| Data updates | Implement the agreed refresh, removal, monitoring, and recovery processes. | Validate platform-side processing and surface ingestion issues. |
| Environments | Confirm application configuration, connectivity, and deployment requirements. | Provide the agreed platform environment and access. |
| Platform settings | Confirm business rules and expected behavior. | Configure the supported capabilities included in scope. |
| Authentication | Supply required identity-provider details and test identities. | Configure applicable platform access. |
| Test fixtures | Define representative users, transactions, and publisher-side data. | Prepare agreed platform-side test objects and settings. |
Configuration may include experiences, auction rules, targeting, attribution, branding, users, and authentication, depending on scope.
Use the inventory feed for the agreed catalog information. Confirm separately how current pricing and availability are validated at serving time.
See Inventory Feeds.
Exit milestone: Required access works, representative records are usable, and configuration supports integration testing.
Sample data can unblock developmentA representative file can support initial configuration and development. Production data processes must be operational before launch unless both teams accept a documented interim process with an owner and replacement date.
Phase 3: Integration and Component Testing
Illustrative window: Days 8–30
Build and validate each component as soon as its prerequisites are ready.
Components to implement and verify
| Component | Validate during development |
|---|---|
| Ad requests | Configured identifiers, candidate selection, targeting context, response handling, and latency. |
| Rendering | Approved designs, assets, sponsored labels, navigation, accessibility, and responsive behavior. |
| Event collection | Impression qualification, click handling, tracking linkage, and conversion submission. |
| Identity and attribution | Consistent identifiers, transaction values, and expected attribution behavior. |
| Campaign controls | Applicable states, schedules, targeting, budgets, funding, and pricing rules. |
| Failure handling | No-fill, timeouts, invalid inputs, bounded retries, and fallback behavior. |
| Data changes | Additions, updates, removals, and relevant eligibility changes. |
| Reporting | Required fields, query behavior, downstream consumption, and data availability. |
Keep test activity identifiable and apply its agreed treatment in reporting and billing.
Use available sample responses or controlled fixtures to unblock development. Record where simulated behavior is used and when live integration evidence must replace it.
See the Implementation Overview.
Exit milestone: In-scope components work independently, defects are tracked, and the complete customer and advertiser test journeys are available.
Phase 4: End-to-End Testing and UAT
Illustrative window: Days 21–40
Begin with completed workflows while other components remain in development.
Use the Testing Checklist to create the project-specific acceptance plan.
Coverage and evidence requirements
Cover successful journeys, invalid inputs, ineligible requests, repeated events, interruptions, recovery, attribution, and reconciliation.
| Test record | What to capture |
|---|---|
| Requirement | The workflow and acceptance criterion being verified. |
| Preconditions | Environment, configuration, permissions, data, and campaign state. |
| Execution | Reproducible steps, run ID, timestamps, and relevant identifiers. |
| Expected result | Observable assertions established before execution. |
| Actual result | Observed behavior with supporting evidence. |
| Status | Pass, Fail, Pending, Blocked, Not Run, or Not Applicable. |
| Resolution | Defect reference, owner, fix, and retest evidence. |
Agree on processing delays, filtering, time zones, currencies, attribution measures, and reconciliation tolerances before comparing results.
Compare equivalent stages. Raw events, accepted events, filtered events, and attributed outcomes can represent different populations.
Exit milestone: Mandatory tests pass, launch-blocking defects are resolved and retested, and designated business and technical owners accept the evidence.
Record accepted exceptions with an owner, rationale, mitigation, and target date.
Match the workflow to available accessThe documented Koddi Ads MCP provides read-only configuration and reporting access. Event submission, campaign changes, browser automation, raw-event inspection, and other execution steps require additional tools and permissions.
Confirm the connections available for your environment. See Koddi Ads MCP.
Phase 5: Launch Preparation
Illustrative window: Days 35–44
Prepare the operating model while testing is underway. Complete the readiness review once the required evidence is available.
Readiness checklist
- Required testing is complete and acceptance is recorded.
- Production configuration, access, data, and initial campaigns are ready.
- Launch-blocking defects are resolved and retested.
- Accepted exceptions have owners and mitigations.
- Reporting and reconciliation meet agreed thresholds.
- Rollout stages and expansion criteria are defined.
- Monitoring and alerts have named owners.
- Stop conditions and rollback procedures are documented.
- Launch and support coverage are confirmed.
- Required business and technical approvers have reviewed readiness.
Exit milestone: Designated owners record Ready, Ready with Accepted Exceptions, or Not Ready, along with the conditions and scope of that decision.
Phase 6: Controlled Launch
Illustrative timing: Day 45, subject to readiness
Start with the agreed placements, campaigns, markets, or traffic allocation.
Run production smoke tests and verify the behavior that can be observed immediately. Continue downstream checks as events, attribution, and reporting become available.
| Area | Initial production validation |
|---|---|
| Customer experience | Ads render correctly and the primary journey remains usable. |
| Delivery | Requests, eligibility, fill, and fallback behave as expected. |
| Measurement | Qualifying events arrive with the required identifiers and context. |
| Financial controls | Spend, pricing, budgets, and funding follow the agreed rules. |
| Reliability | Errors, latency, and recovery remain within the agreed limits. |
| Reporting | Data becomes available within the expected processing windows. |
Increase exposure when the agreed criteria pass. If a stop condition is met, follow the documented pause or rollback procedure.
Exit milestone: Initial production behavior is verified and the rollout can continue within its approved boundaries.
Phase 7: Stabilization
Timing: An agreed post-launch window
Reconcile production results, investigate discrepancies, and transfer ownership to the ongoing operating teams.
- Production behavior and reconciliation are accepted.
- Remaining issues have owners, priorities, and next steps.
- Operating teams have the required access and documentation.
- Monitoring, escalation, and recovery procedures are understood.
- Routine reporting and business reviews are scheduled as agreed.
- Regression checks are defined for releases and material configuration changes.
- Ownership of deferred phases is recorded.
Exit milestone: Both teams accept the production implementation and the ongoing operating model.
Related Resources
Customize the Sample Implementation Scope.
Establish your cadence using Implementation Meetings.
Validate the integration using the Testing Checklist.